Gauri Parbati Nirman Sewa Pvt. Ltd has successfully completed numbers of road construction. From construction of new roads to upgrading and improvement of existing roads, GPNS has been continuously serving in the construction of road in Nepal.

                                                                                                                        Road Construction Works
S.N. Name of Project Name of Client  Agreement Date Completion Date  Total Contract Amount NRs. (Including VAT) Total Final Received Amount NRs. (Including VAT)
1 Upgrading/Improvement of Chovar Dakchinkali Section of Balkhu- Dakchinkali Road Department of Roads Road Improvement and Development Project Directorate Bhaktapur Nagarkot Sipaghat Balkhu Dakchinkali Road Project Battisputali, Kathmandu 03 June, 2015 24 October, 2020 217,019,106.95 232,262,957.18
2 Construction of Municipal Sewerage, River Training, Service Road and Allied Works Ch 0+000 to 2+900 on both sides, from the confluence of Bagmati & Bishnumati River to Upstream, Contract No: BAPIDP-B1/071-72 High Powered Committee for Integrated Development of the Bagmati Civilization, Guheshwori, Kathmandu 03 December, 2015 26 November, 2019 679,019,291.53 864,646,068.62
3 Upgrading/Improvement of Lamosanghu-Mude Section of Lamosanghu-Tamakoshi-Jiri Road (Ch 0+000 to 25+000) Department of Roads Road Improvement and Development Project Directorate Bhaktapur Nagarkot Sipaghat Balkhu Dakchinkali Road Project Battisputali, Kathmandu 03 June, 2015 24 October, 2020 392,652,387.87 542,570,719.31
4 Upgrading of Atmaram path (0+000 to 13+005), Contract No: SNRTP-PAR-W-NCB-18.01-UG-070-71 Infrastructure Development Office, Birgunj, Parsa 06 April, 2016 06 January, 2019 90,841,426.09 85,717,635.23
5 Upgrading & widening of earthen road to double lane carriageway asphalt concrete pavement including construction of side drain, retaining structure etc in Thankot Chitlang Road (ch 1+640 to 3+000), Contract No: TCRP/3371104/074/075-001 Federal Supervision and Monitoring Office, Thankot-Chitlang Road Project, Kalanki, Kathmandu 26th Feb, 2018 16th Sept, 2019 75,299,291.72 68,651,264.82
6 Construction and Rehabilitation (damaged after earthquake) of Araniko Highway, Barhabise-Kodari Sector, Contract No: DROCHT/301801-4/073/74-150 Road Division Charikot 24th April, 2017 13th June, 2018 34,940,101.89 31,855,888.29
7 Supply and Installation of Steel W – Beam Crash Barrier (Road Safety works) on Tripurasundari (Baitadi) – Satabanjh – Gokuleshwor – Darchula & Khodpe – Bajhang Road, Contract No. RSSD – DOR – W – ICB – 1.1 Road Safety Support Project, Kupondol Jwagal, Lalitpur 13 July, 2015 6 July, 2017 89,308,309.37 92,029,529.68
8 Supply and Installation of Steel W – Beam Crash Barrier (Road Safety works) on Tallodungeshwor – Jumla Road, Contract No. RSSD – DOR – W – ICB – 1.3 Road Safety Support Project, Kupondol Jwagal, Lalitpur 13 July, 2015 30 June, 2017 74,545,293.52 74,545,293.52
9 Construction of Guide wall, Gravelling work, Storm Water Drainage and Subgrade Preparation(KLPP), Contract No.Kamerotar – 01/070/071 KVDA, KLPP, Madhyapur Thimi 10/22/2070 1/30/2073 367,626,923.25 369,250,750.29
10 Strengthening (Asphalt Concrete) of Runway, Taxiway, Apron and other associated works at Taplejung Airport, Suketar,Taplejung, CAAN/AED/TPJ/Asphalt Concrete/070-071/03 CAAN, Aerodrom Engineering Department, Babarmahal, Kathmandu. 10/23/2070 10/23/2074 81,365,038.99 81,365,038.99
11 Periodic Maintenance of Mahakali Highway (Syaule Bhalumara Section), Seti Highway(Syaule Korayal Sectiion) an Silgadi Sanfe Road, Silgadhi, Guder Section, Contract No. RSDPAF -W – SYPM – NCB – FWR – Doti – 1B Babarmahal, Kathmandu. 15 July, 2012 3/29/2015 68,240,098.47 68,239,720.48
12 Black Top, Drain, Masonry Wall works at Suryabinayak piolot baba Road, Contract No: SAARC/DROBKT/3371494/071/072-001   25-Aug-14 14/1/2015 60,652,817.80 69,532,075.15
13 Rehabilitation, Upgrading and widening of Lainchaur – Maharajgunj – Budanildantha Road, Contract No.KVRIP/3371494/069/070/010 DRO, KVRIP, Kathmandu 17-Mar-13 running 108,130,595.32 108,130,595.32
14 Upgrading and Widening of Jadibuti – Pepsi – Manohra Road Improvement works, Contract No.KVRIP/3371494/070/071/001 DRO, KVRIP, Kathmandu 1/27/2014 6/14/2016 143,085,573.30 165,415,922.33
15 Satdobato – Karmanasa Bridge Road, Contract No.131/068/069/149 DOR,Lalitpur 7/11/2012 4/2/2014 138,284,750.90 151,755,573.56
16 Ugrading and Maintenance  of Madredhunga – Ghadgabhanjyang – Gorshang – Dansing Road, contract No. RAIDP/W/NCB/NUW – 16.6/RI/068/069 DTO, Bidur, Nuwakot 1-Jun-12 30-Nov-13 14,658,633.35 17,030,471.15
17 Upgrading Works of Chhinchu – Jajarkot Road under contract No.:RSDPAF-W-UP-ICB-CJ-5C Chhinchu – Jajarkot Road Project, Babarmahal, Kathmandu 4/2/2012 5/21/2014 151,535,979.81 174,254,646.20
18 Consftruction of Guide wall, Storm Water Drainage and Subgrade Preparation under Kamerotar Land Pooling Project under Contract No.Kamerotar01/068/069 KVDA, Kamerotar Land Pooling Project, Thimi 7/1/2069 6/30/2070 49,501,868.47 49,358,590.00
19 Expansion of Sallaghari Byasi Road, Contract No. DROBKT/3371494/10/069/070 DOR,  CRRD, Division Road Office, Bhaktapur 2/7/2069 30/6/2070 107,302,421.35 116,508,604.31
20 Road Construction works at Ganeshchowk – Chiyobhanjyang sector in Panchthar, Contract No. MHH/ES/1 – 12.13&14/068/069 DOR,  Pushpalal Hihgway Project, Eastern Sector, Kathmandu. 1/8/2069 6/3/2070 55,501,137.63 49,717,867.69
21 Construction works at Ganeshchowk – Chiyobhanjyang sector in Panchthar, Contract No. MHH/ES/1 – 13/066/067 DOR,  Pushpalal Hihgway Project, Eastern Sector, Kathmandu. 11/28/2066 9/30/2068 17,761,282.27 18,810,621.20
22 Strenthening of Runway, Taxiway and Apron under CAAN, Simikot Airport, Humla, contract no.01/Sim/064 – 65/CED/CAAN CAAN/Humla Airport Project   2011.11.14 117,213,604.54 117,175,688.11
23 Phidim – Taplejung Road Project, RCSP/NCB/PT – 02 DOR,  RCSP, Phidim – Taplejung Road Project, Panchthar. 7-Apr-09 30-Jun-11 79,254,123.09 87,265,832.83
24 Periodic Maintenace of Pipalbot – Naubise and Naubise – Simle Road., Contract No. RSDP-FYPM/PNS/NCB-02 DOR, Rehabilitation Component, Kathmandu 8-Aug-09 31-Jan-11 59,860,801.14 65,891,642.16
25 Periodic Maintenace of Tansen Municipality – Kaligandaki, East –  West  and Siddhartha (Highway). DoR, WRRDi, Pokhara 1-Feb-10 16-Jul-11 40,410,696.45 38,254,035.75
26 Access Road and Internal Roads at Bhairahwa EPZ Special Economic Zone Project Baisakh 4, 2066 Falgun 15, 2066 66,296,051.53 66,296,051.53